File #: #19-157    Version: 1 Name:
Type: RESOLUTIONS Status: Passed
File created: 4/9/2019 In control: City Council
On agenda: 4/15/2019 Final action: 4/16/2019
Title: RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO (1) IDENTIFYING FY 2018/19 PAVEMENT REPAIR PROJECT AS SENATE BILL 1 (SB1) ROAD REPAIR AND ACCOUNTABILITY ACT MAINTENANCE-OF-EFFORT PROJECT IN AN AMOUNT EQUAL TO OR GREATER THAN $464,941; (2) APPROVING AND ADOPTING THE PLANS AND SPECIFICATIONS FOR THE FY 2018/19 PAVEMENT REPAIR PROJECT; (3) AWARDING A CONTRACT FOR THE FY 2018/19 PAVEMENT REPAIR PROJECT AND AUTHORIZING THE CITY MANAGER TO EXECUTE AN AGREEMENT WITH BAY CITIES PAVING & GRADING, INC. IN THE AMOUNT OF $1,206,109 WITH A 15% CONTINGENCY FOR A TOTAL CONTRACT AUTHORIZATION OF $1,387,025; AND (4) APPROPRIATING $830,138 FROM THREE SOURCES TO THE ANNUAL PAVEMENT REHABILITATION PROGRAM
Attachments: 1. RESO 2019-056 FY18-19 Pavement Proj. SB1 road repair MAR-600, 2. Bid-Opening Spreadsheet MAR-600 (signed).pdf, 3. Contract MAR-600 (signed by Bay Cities).pdf
PREPARED BY: ALLAN PANGANIBAN DATE OF MEETING: 04/15/19
SUBJECT:
TITLE
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO (1) IDENTIFYING FY 2018/19 PAVEMENT REPAIR PROJECT AS SENATE BILL 1 (SB1) ROAD REPAIR AND ACCOUNTABILITY ACT MAINTENANCE-OF-EFFORT PROJECT IN AN AMOUNT EQUAL TO OR GREATER THAN $464,941; (2) APPROVING AND ADOPTING THE PLANS AND SPECIFICATIONS FOR THE FY 2018/19 PAVEMENT REPAIR PROJECT; (3) AWARDING A CONTRACT FOR THE FY 2018/19 PAVEMENT REPAIR PROJECT AND AUTHORIZING THE CITY MANAGER TO EXECUTE AN AGREEMENT WITH BAY CITIES PAVING & GRADING, INC. IN THE AMOUNT OF $1,206,109 WITH A 15% CONTINGENCY FOR A TOTAL CONTRACT AUTHORIZATION OF $1,387,025; AND (4) APPROPRIATING $830,138 FROM THREE SOURCES TO THE ANNUAL PAVEMENT REHABILITATION PROGRAM

Label
CITY MANAGER RECOMMENDATION
Recommendation
Adopt Resolution

BODY
COMPLIANCE STATEMENTS
Build a Healthy Community: Priority 100.11 - Develop Public Facilities for Active Living is an adopted policy item under the FY 2019-21 City Council Priority Workplan, adopted on March 1, 2019 through Resolution 2019-029.

CEQA Compliance Statement
The project is exempt from the California Environmental Quality Act ("CEQA") pursuant to Public Resources Code sections 21083 and 21084 and 14 C.C.R. Sec. 15301 because it consists of the rehabilitation of existing street pavement within the City. There will be no increase in the number of lanes and no scenic resource will be altered or removed. A CEQA Notice of Exemption is in process of being filed with the Contra Costa County Clerk.

BACKGROUND

The FY 2018/19 Pavement Repair Project is part of the City's ongoing effort to maintain its streets. Upon the completion of the project, the various streets' Pavement Condition Index (PCI) will be raised. Pedestrian access will also be improved with better sidewalks and ADA compliant curb ramps.

On April 28, 2017, then Governor Brown signed Senate Bill 1 (SB1) (Chapter 5, Statutes of 2017), known as th...

Click here for full text