Title: RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO ACCEPTING WORK PERFORMED BY JOHN CLAY GENERAL ENGINEERING CONTRACTOR, INC. FOR THE SAN PABLO POLICE DEPARTMENT FOUNDATION REPAIR PROJECT (PDT-ELV) AS COMPLETE AND DIRECTING THAT A NOTICE OF COMPLETION BE PREPARED AND FILED WITH THE COUNTY RECORDER
Attachments: 1. RESO 2018-113 NOC PD foundation repair PDT-ELV
PREPARED BY: RONALYN NONATO DATE OF MEETING: 08/06/18
SUBJECT:
TITLE
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO ACCEPTING WORK PERFORMED BY JOHN CLAY GENERAL ENGINEERING CONTRACTOR, INC. FOR THE SAN PABLO POLICE DEPARTMENT FOUNDATION REPAIR PROJECT (PDT-ELV) AS COMPLETE AND DIRECTING THAT A NOTICE OF COMPLETION BE PREPARED AND FILED WITH THE COUNTY RECORDER

Label
CITY MANAGER RECOMMENDATION
Recommendation
Adopt Resolution

BODY
COMPLIANCE STATEMENTS
CIP 2015-2017
Building Maintenance is an adopted policy item under the Infrastructure policy area of the FY2018-21 City Council Priority Workplan, effective November 1, 2017.

CEQA Compliance Statement
The project is categorically exempt under the California Environmental Quality Act, Section 15302 of the CEQA Regulations, Replacement or Reconstruction. A Notice of Exemption was filed with the Contra Costa County Clerk on June 20, 2017.

BACKGROUND
The existing building that houses the Police Department at 13880 San Pablo Avenue was constructed in the late 1980's. The elevator was added to the building a few years after the original construction. In 1996, the building was converted to its current use as a police station. After the 2014 Napa earthquake, settlement was observed in the vicinity of the elevator. In 2015, further evidence of settlement was observed.

On April 18, 2016, Council adopted Resolution 2016-0149 authorizing a geotechnical consultant agreement with Miller Pacific Engineering Group (Miller Pacific) to perform geotechnical evaluation associated with the Police Department Elevator Hall Foundation Repair Project. On-call consultant, Bellecci & Associates, with sub-consultant Miller Pacific, was hired to perform geotechnical engineering services for the project. Per the consultant's findings, their design recommendation to address the settlement problem included localized underpinning of the elevator structure using helical anchors and removal and replacement of the existing s...