Title: RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO (1) ACCEPTING AND APPROPRIATING SB1 - LOCAL PARTNERSHIP GRANT PROGRAM FUNDS IN THE AMOUNT OF $3,200,000 AND DESIGNATE THESE FUNDS TO THE RUMRILL BOULEVARD COMPLETE STREETS PROJECT (RUM-CST); AND (2) AUTHORIZING THE CITY MANAGER TO ENTER INTO AN AGREEMENT WITH PARK ENGINEERING, INC. FOR RUMRILL BOULEVARD COMPLETE STREETS CONSTRUCTION MANAGEMENT/INSPECTION SERVICES IN THE AMOUNT OF $1,124,620 WITH A 15% CONTINGENCY FOR A TOTAL AUTHORIZATION OF $1,293,313
Attachments: 1. RESO 2018-109 Accept SB-1 and Contract for CM Service for RUM-CST, 2. CM Consultant Agreement Draft 7.23.pdf
PREPARED BY: AMANDA BOOTH DATE OF MEETING: 08/06/18
SUBJECT:
TITLE
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO (1) ACCEPTING AND APPROPRIATING SB1 - LOCAL PARTNERSHIP GRANT PROGRAM FUNDS IN THE AMOUNT OF $3,200,000 AND DESIGNATE THESE FUNDS TO THE RUMRILL BOULEVARD COMPLETE STREETS PROJECT (RUM-CST); AND (2) AUTHORIZING THE CITY MANAGER TO ENTER INTO AN AGREEMENT WITH PARK ENGINEERING, INC. FOR RUMRILL BOULEVARD COMPLETE STREETS CONSTRUCTION MANAGEMENT/INSPECTION SERVICES IN THE AMOUNT OF $1,124,620 WITH A 15% CONTINGENCY FOR A TOTAL AUTHORIZATION OF $1,293,313

Label
CITY MANAGER RECOMMENDATION
Recommendation
Adopt Resolution

BODY
COMPLIANCE STATEMENTS
Infrastructure - Admin/Operations - (6) Capital Improvement Projects, (6.2.13) Rumrill Complete Streets Corridor Mobility Plan is an adopted policy item under the FY 2018-21 City Council Priority Workplan, effective November 1, 2017.

CEQA Compliance Statement
This project is categorically exempt under the California Environmental Quality Act, Section 15301, Existing Facilities (Class 1) of the CEQA Regulations, on the basis that the project involves repair and minor alteration to the existing public streets, sidewalks, gutters and similar facilities. The Notice of Exemption was filed and recorded with the Contra Costa County Clerk on January 7, 2018. Since the project is also receiving federal funding the project was also determined to categorically exempt under the National Environmental Policy Act (NEPA), Section 23 CFR 771.117(c): activity(c)(3). The Notice of Exemption for NEPA was filed on March 14, 2018 by the California Department of Transportation (Caltrans).

BACKGROUND
The City of San Pablo, in collaboration with the City of Richmond, commissioned a Complete Streets Study that considered options for improving Rumrill Boulevard for all road users. This study, which was finalized in 2015, developed a project scope and 30 percent plans for improvements. The Rumrill Boulevard Comp...