File #: #20-053    Version: 1 Name:
Type: RESOLUTIONS Status: Passed
File created: 1/27/2020 In control: City Council
On agenda: 3/2/2020 Final action: 3/3/2020
Title: RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO ACCEPTING WORK PERFORMED BY GHILOTTI BROTHERS, INC. FOR THE SAN PABLO AVENUE COMPLETE STREETS PROJECT (SPA-CST) AS COMPLETE AND DIRECTING THAT A NOTICE OF COMPLETION BE PREPARED AND FILED WITH THE COUNTY RECORDER
Attachments: 1. RES 2020-025 NOC Accept Ghilotti Bros SPA-CST
PREPARED BY: ALLAN A. PANGANIBAN DATE OF MEETING: 03/02/20
SUBJECT:
TITLE
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO ACCEPTING WORK PERFORMED BY GHILOTTI BROTHERS, INC. FOR THE SAN PABLO AVENUE COMPLETE STREETS PROJECT (SPA-CST) AS COMPLETE AND DIRECTING THAT A NOTICE OF COMPLETION BE PREPARED AND FILED WITH THE COUNTY RECORDER

Label
CITY MANAGER RECOMMENDATION
Recommendation
Adopt Resolution

BODY
COMPLIANCE STATEMENTS
Build a Healthy Community: Priority 100.11 - Develop Public Facilities for Active Living is an adopted policy under the FY 2019-21 Council Priority Workplan, adopted on March 1, 2019 through Resolution 2019-029.

CEQA Compliance Statement
This project was categorically exempt under the California Environmental Quality Act (CEQA), Section 15301 (c), on the basis that the project involves repair and minor alteration to the existing streets, sidewalks, gutters, and similar facilities. The Notice of Exemption was filed and recorded with the Contra Costa County clerk on October 24, 2016.

The State has also determined that this project has no significant impacts on the environment as defined by the National Environmental Policy Act (NEPA), and that there are no unusual circumstances as described in 23 CFR 771.117 (b). The NEPA determination was approved by the State on October 12, 2016 and revalidated on April 4, 2017.

BACKGROUND
On February 20, 2018, through Resolution 2018-019, City Council awarded a construction contract for the San Pablo Avenue Complete Streets Project ("Project") to Ghilotti Brothers, Inc. ("Contractor"). City Council also authorized the City Manager to execute an agreement in the amount of $5,283,721.

The Project included improving multimodal access, safety and connection along the San Pablo Avenue corridor by modifying the existing road section adding Class 2 bike lanes in both directions of travel. The Project was constructed to include sidewalk installation on the west side of San Pablo Ave...

Click here for full text