Title: RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO (1) APPROVING AND ADOPTING THE PLANS AND SPECIFICATIONS FOR THE WILDCAT CREEK RESTORATION AND GREENWAY TRAIL PROJECT; (2) AWARDING A CONTRACT FOR THE PROJECT AND AUTHORIZING THE CITY MANAGER TO EXECUTE A CONTRACT WITH THE LOWEST RESPONSIVE AND RESPONSIBLE BIDDER, GHILOTTI CONSTRUCTION, IN THE AMOUNT OF $3,159,966 WITH A 15% CONTINGENCY FOR A TOTAL CONTRACT AUTHORIZATION OF $3,633,960; (3) AUTHORIZING THE CITY MANAGER TO AMEND AN EXISTING $404,991 AGREEMENT WITH RESTORATION DESIGN GROUP FOR PROJECT DESIGN SERVICES TO ADD $25,000 FOR SERVICES REQUIRED FOR CONSTRUCTION PHASE SERVICES WITH A 15% CONTINGENCY, FOR A TOTAL AMENDMENT AUTHORIZATION OF $28,750; AND (4) AUTHORIZING THE CITY MANAGER TO PROCEED WITH A FORMAL SOLICITATION PROCESS FOR A FUTURE PUBLIC ART PROJECT TO BE DEVELOPED INDEPENDENTLY
Attachments: 1. RES 2020-008 Ghilotti Const award RDG Amend WCC-TRL, 2. WCC-TRL Sample Ghilotti Contract - Staff Report attach, 3. WCC-TRL RDG Amend Proposal 2019.11.08 WG ASR 3_rev 3
PREPARED BY: RONALYN NONATO DATE OF MEETING: 01/21/20
SUBJECT:
TITLE
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO (1) APPROVING AND ADOPTING THE PLANS AND SPECIFICATIONS FOR THE WILDCAT CREEK RESTORATION AND GREENWAY TRAIL PROJECT; (2) AWARDING A CONTRACT FOR THE PROJECT AND AUTHORIZING THE CITY MANAGER TO EXECUTE A CONTRACT WITH THE LOWEST RESPONSIVE AND RESPONSIBLE BIDDER, GHILOTTI CONSTRUCTION, IN THE AMOUNT OF $3,159,966 WITH A 15% CONTINGENCY FOR A TOTAL CONTRACT AUTHORIZATION OF $3,633,960; (3) AUTHORIZING THE CITY MANAGER TO AMEND AN EXISTING $404,991 AGREEMENT WITH RESTORATION DESIGN GROUP FOR PROJECT DESIGN SERVICES TO ADD $25,000 FOR SERVICES REQUIRED FOR CONSTRUCTION PHASE SERVICES WITH A 15% CONTINGENCY, FOR A TOTAL AMENDMENT AUTHORIZATION OF $28,750; AND (4) AUTHORIZING THE CITY MANAGER TO PROCEED WITH A FORMAL SOLICITATION PROCESS FOR A FUTURE PUBLIC ART PROJECT TO BE DEVELOPED INDEPENDENTLY

Label
CITY MANAGER RECOMMENDATION
Recommendation
Adopt Resolution

BODY
COMPLIANCE STATEMENTS
Major Policy Goal: Build a Healthy Community, 100.11 Develop Public Facilities for Active Living (Parks, Open Space, Sidewalks, Trails, Bike Lanes, etc.) is an adopted policy item under the FY 2019-21 City Council Priority Workplan, effective March 1, 2019.

CEQA Compliance Statement
The proposed project completed CEQA review in 2013 and it was determined to be categorically exempt in accordance with Sections 15304 and 15333 of the CEQA Guidelines, on the basis that this project involves minor alterations to land and small habitat restoration. The Notice of Exemption was filed with the County on May 25, 2018.

BACKGROUND
The Wildcat Creek Restoration and Greenway Trail project will restore 2,200 linear feet of Wildcat Creek and include construction of a 2,100 linear foot greenway-trail with a Class I bike/pedestrian path, landscaping and pedestrian amenities between Church Lane and Vale Road. Currently that section of Wildcat Creek is severely al...