File #: #19-412    Version: 1 Name:
Type: RESOLUTIONS Status: Passed
File created: 9/5/2019 In control: City Council
On agenda: 9/16/2019 Final action: 9/17/2019
Title: RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO (1) AUTHORIZING THE EMERGENCY PROCUREMENT AND INSTALLATION OF HVAC EQUIPMENT FOR THE POLICE ADMINISTRATIVE FACILITY (4/5 VOTE); (2) AWARDING THE BID TO SH MECHANICAL, INC. FOR THE PURCHASE OF A 20-TON "CARRIER" ROOFTOP COOLING UNIT, TO INCLUDE EQUIPMENT, HARDWARE, ANCILLARY INSTALLATION AND A ONE-YEAR WARRANTY, AT THE POLICE DEPARTMENT IN THE AMOUNT OF $67,825 INCLUDING A 15% CONTINGENCY FOR A TOTAL NOT TO EXCEED $77,999; AND (3) AUTHORIZING THE CITY MANAGER TO ENTER INTO AN AGREEMENT WITH SH MECHANICAL, INC.
Attachments: 1. RES 2019-143 SH Mechanical PD HVAC System, 2. S H Mechanical Bid.pdf, 3. S H Mechanical Contractor License.pdf, 4. S H Mechanical DIR.pdf, 5. Marina Mechanical Bid.pdf, 6. Marina Mechanical Contractor License.pdf, 7. Marina Mechanical DIR.pdf, 8. Richards Heating and Air Bid.pdf, 9. Richards Contract License.pdf, 10. Richards Heating and Air DIR.pdf
PREPARED BY: LT. DAN WIEGERS DATE OF MEETING: 09/16/19
SUBJECT:
TITLE
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO (1) AUTHORIZING THE EMERGENCY PROCUREMENT AND INSTALLATION OF HVAC EQUIPMENT FOR THE POLICE ADMINISTRATIVE FACILITY (4/5 VOTE); (2) AWARDING THE BID TO SH MECHANICAL, INC. FOR THE PURCHASE OF A 20-TON "CARRIER" ROOFTOP COOLING UNIT, TO INCLUDE EQUIPMENT, HARDWARE, ANCILLARY INSTALLATION AND A ONE-YEAR WARRANTY, AT THE POLICE DEPARTMENT IN THE AMOUNT OF $67,825 INCLUDING A 15% CONTINGENCY FOR A TOTAL NOT TO EXCEED $77,999; AND (3) AUTHORIZING THE CITY MANAGER TO ENTER INTO AN AGREEMENT WITH SH MECHANICAL, INC.

Label
RECOMMENDATION
Recommendation
Adopt Resolution

BODY
COMPLIANCE STATEMENTS
This is not a specific item in the FY 2019-21 City Council Priority Workplan, effective March 1, 2019, but is required for continued efficient city operations.

CEQA Compliance Statement
This proposed action is exempt from the provisions of the California Environmental Quality Act (CEQA), under CEQA Guidelines section 15302 for the replacement or reconstruction of existing facilities and section 15061(b)(3) in that it can be seen with certainty that there is no possibility that the activity in question may have a significant effect on the environment.

BACKGROUND
The Police Department has two 20-ton air conditioning units which were manufactured and installed in 1996 (21 years ago). Each unit controls the air conditioning for one-half of the building. The Police Department's HVAC system also consists of a hot water boiler system for heat. These systems work in conjunction to regulate the temperature inside the Police Department.

In July 2017, the unit controlling air conditioning for the Administration, Investigations, Records Section and portions of the Temporary Holding Facility stopped producing cool air. The failing unit caused a significant heat increase in the aforementioned areas of the Police Station. That 20-ton air con...