San Pablo header
File #: #19-129    Version: 1 Name:
Type: RESOLUTIONS Status: Passed
File created: 3/18/2019 In control: City Council
On agenda: 4/1/2019 Final action: 4/2/2019
Title: RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO AUTHORIZING THE CITY MANAGER TO AMEND AN EXISTING AGREEMENT WITH AMPCO NORTH, INC. FOR CONSTRUCTION AND DEMOLITION SERVICES FOR THE 2023 VALE ROAD BUILDING DEMOLITION PROJECT TO ADD $45,000 FOR SERVICES REQUIRED FOR THE ABATEMENT OF ADDITIONAL ASBESTOS CONTAINING MATERIALS (ACM) AND ASBESTOS CONTAINING CONSTRUCTION MATERIALS (ACCM) FOR A TOTAL PROJECT AUTHORIZATION OF $172,095 AND TO APPROPRIATE $25,936 FROM MEASURE WW URBAN CREEKS GRANT PROGRAM
Attachments: 1. RES 2019-046 AMPCO demo WCC-TRL, 2. AMPCO revised COR 001.pdf

PREPARED BY:   RONALYN NONATO                                          DATE OF MEETING:   04/01/19

SUBJECT:                     

TITLE

RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO AUTHORIZING THE CITY MANAGER TO AMEND AN EXISTING AGREEMENT WITH AMPCO NORTH, INC. FOR CONSTRUCTION AND DEMOLITION SERVICES FOR THE 2023 VALE ROAD BUILDING DEMOLITION PROJECT TO ADD $45,000 FOR SERVICES REQUIRED FOR THE ABATEMENT OF ADDITIONAL ASBESTOS CONTAINING MATERIALS (ACM) AND ASBESTOS CONTAINING CONSTRUCTION MATERIALS (ACCM) FOR A TOTAL PROJECT AUTHORIZATION OF $172,095 AND TO APPROPRIATE $25,936 FROM MEASURE WW URBAN CREEKS GRANT PROGRAM

 

Label

CITY MANAGER RECOMMENDATION

Recommendation

Adopt Resolution

 

Body

Compliance statements

Major Policy Goal: Build A Healthy Community - Develop Public Facilities for Active Living is an adopted policy item under the FY 2019-21 City Council Priority Workplan, effective March 1, 2019. 

 

CEQA Compliance Statement

This demolition project is part of the future Wildcat Creek Restoration and Greenway Trail Project (WCC-TRL) project. The said project completed CEQA review in 2013 but was reevaluated and filed in May of 2018 due to some minor changes. The project was determined to be categorically exempt in accordance with Section 15333 Class 33, Small Habitat Restoration project of the CEQA Guidelines, on the basis that this project involves minor alterations to land and small habitat restoration.

 

BACKGROUND

The 2023 Vale Road Building Demolition Project is a portion of the Wildcat Creek Restoration and Urban Greenway Trail Project (WCC-TRL). The WCC-TRL project will restore 2,200 linear feet of Wildcat Creek and include a 2,100 linear foot greenway-trail with a Class I bike/pedestrian path, landscaping and pedestrian amenities. The 2023 Vale Road lot, which is City-owned, consists of two building facilities: a 1-story bungalow and a 2-story medical building. To properly grade or restore the creek and install the greenway-trail, this project phase will demolish and abate approximately 6,900 square feet of the 1-story bungalow building. Once demolished, the existing lot will make way for a new creek-side trail and a new parking lot, which will be constructed as part of the bigger Wildcat Creek Project. 

 

During the abatement process for the 2023 Vale Road Building Demolition Project, additional asbestos containing materials (ACM) and asbestos containing construction materials (ACCM) were discovered.

 

As a result of the need for this additional abatement, staff is recommending authorization of an amendment to the existing contract with AMPCO North, Inc. to complete the project. Staff has obtained a change order request from AMPCO North, Inc. to perform the needed tasks (see Attachment A) for a lump sum negotiated cost of $40,000, which is over the 15% project contingency approved at award of $19,064. This additional work will modify AMPCO North’s contract with the City as follows:

 

AMPCO North, Inc.

Amount

With 15% Contingency

Additional funds needed

Original Contract

$127,094.22

$19,064

 

Contract Amendment

$40,000

 

$20,936

Total Contract Amount

$167,094.22

 

$20,936

 

An additional $5,000 contingency is also being requested so as to not delay the contractor if other unforeseen materials or changes to the contract are necessary.

 

The total requested amount is $25,936.

 

FISCAL IMPACT

Funding for the amendment of this contract exists under the $800,000 in Measure WW Urban Creeks Grant Program awarded to the City for this project and accepted and appropriated by the City in November 2018 (Resolution 2018-146).  Therefore, the fiscal impact of this item is to allocate an additional $25,936 of the original $800,000 award for a total of $172,095 to the 2023 Vale Road Bungalow Demolition Project (WCC-TRL) as shown in the table below.

 

 ACTION

FROM:  Fund / Account Code

 AMOUNT

TO:  Fund / Account Code

 AMOUNT

Appropriate 

Measure WW Urban Creeks Grant Program 320-3203-33403

 $25,936

 320-3203-43600-WCC-TRL