Title: CONSIDER ADOPTING A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO (1) ACCEPTING WORK PERFORMED BY CENTRAL ROOFING, INC. FOR THE COMMUNITY CENTER ROOF REPLACEMENT PROJECT (0107) AS COMPLETE, AND (2) DIRECTING CITY ENGINEER TO FILE A NOTICE OF COMPLETION WITH THE COUNTY RECORDER CEQA: This proposed action is not a project as defined by CEQA.
Attachments: 1. Att A - Resolution Comm Ctr Roof Accept Project as Complete 2025-01-21
PREPARED BY: ALLAN A. PANGANIBAN DATE OF MEETING: 01/21/2025
SUBJECT:
TITLE
CONSIDER ADOPTING A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO (1) ACCEPTING WORK PERFORMED BY CENTRAL ROOFING, INC. FOR THE COMMUNITY CENTER ROOF REPLACEMENT PROJECT (0107) AS COMPLETE, AND (2) DIRECTING CITY ENGINEER TO FILE A NOTICE OF COMPLETION WITH THE COUNTY RECORDER

CEQA: This proposed action is not a project as defined by CEQA.


Label
CITY MANAGER RECOMMENDATION
Recommendation
Adopt Resolution

BODY
COMPLIANCE STATEMENTS
FY 2023-2025 Council Priority Workplan Compliance Statements:
Build a Healthy Community is a Major Policy Goal contained in the Fiscal Year 2023-25 City Council Priority Workplan, effective March 1, 2023.

CEQA Compliance Statement
This Project was previously determined to be categorically exempt from environmental review pursuant to CEQA Guidelines Section 15301, Existing Facilities, as it consists of operation, repair, maintenance, permitting, leasing, licensing, or minor alteration of existing public or private structures, facilities, mechanical equipment, or topographical features, involving negligible or no expansion of use beyond that existing at the time of the lead agency's determination. The CEQA Notice of Exemption was filed with the County Recorder on July 26, 2024.

BACKGROUND
The project goal was to replace the Community Center Roof which consisted of clay tile materials. It started experiencing leaks in 2019. The new roof consists of standing seam metal roof.

The roof materials were purchased from a vendor who participates in the California Multiple Award Schedules (CMAS) program provided by California's Department of General Services. On June 10, 2024, City Council authorized the purchase of roofing materials for the roof replacement project pursuant to Resolution 2024-082.

City Council awarded the construction contract on July 1, 2024 pursuant to Resolution 2024-091 to Central Roofing, Inc. in the amount of ...

Click here for full text