PREPARED BY: CHRISTIAN LARREYNAGA DATE OF MEETING: 05/19/2025
SUBJECT:
TITLE
CONSIDER ADOPTING RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO (1) TERMINATING, BY FOUR-FIFTHS VOTE, THE EMERGENCY PROCUREMENT ACTIONS UNDERTAKEN BY THE CITY MANAGER PURSUANT TO PUBLIC CONTRACT CODE SECTION 22050 AND SAN PABLO MUNICIPAL CODE SECTION 3.16.110.A FOR THE STORM DRAIN REPAIR WORK AT 1850 MESA BUENA AVENUE; (2) ACCEPTING WORK PERFORMED BY GOLDEN BAY CONSTRUCTION, INC. FOR EMERGENCY STORM DRAIN REPAIRS AT 1850 MESA BUENA AVENUE FOR THE LEROY HEIGHTS STORM DRAIN REPAIR PROJECT (0306) AS COMPLETE; AND (3) DIRECTING CITY ENGINEER TO FILE A NOTICE OF COMPLETION WITH THE COUNTY RECORDER.
CEQA: This project was assessed and determined to be Categorically Exempt under CEQA Guidelines Section 15301(b), which covers the operation, repair, and maintenance of Class 1 existing publicly owned utility facilities. The CEQA Notice of Exemption (NOE) was filed at the Contra Costa County Clerk's Office on April 8, 2025.
Label
CITY MANAGER RECOMMENDATION
Recommendation
Adopt Resolution
BODY
COMPLIANCE STATEMENTS
FY 2025-2027 Council Priority Workplan Compliance Statements:
Item 513 - Continue Efforts to Support Hillside Protection and Sustain City Drainage Infrastructure is a major policy goal contained in the FY 2025-27 City Council Priority Workplan, adopted on April 7, 2025.
BACKGROUND
On April 21, 2025, the City Council ratified, by unanimous vote, emergency actions previously taken by the City Manager (Resolution 2025-049) pursuant to Public Contract Code Section 22050 and San Pablo Municipal Code Section 3.16.110.a. This action included entering into a contract with Golden Bay Construction for $52,360 and authorization for emergency procurement actions.
A Notice to Proceed was issued for April 15, 2025, allowing Golden Bay Construction Inc. to begin emergency work, with an expected completion within 28 calendar days.
Golden Bay Construction began excavation ...