File #: 25-043    Version: 1 Name:
Type: Periodic Report Status: Passed
File created: 12/19/2024 In control: City Council
On agenda: 1/21/2025 Final action: 1/21/2025
Title: CONSIDER ADOPTING RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO (1) ACCEPTING WORK PERFORMED BY MICHAEL PAUL COMPANY INC FOR THE HAPPY FRIDAY PARK (ORIGINALLY BID AS BUSH AVENUE POCKET PARK) PROJECT (0502) AS COMPLETE; (2) DIRECTING A NOTICE OF COMPLETION TO BE PREPARED AND FILED WITH THE COUNTY RECORDER; AND (3) RE-ALLOCATING UNUSED APPROPRIATED FUNDS FROM THE HAPPY FRIDAY PARK (0502) IN THE AMOUNT OF $105,234.14 TO THE MCNEIL PARK PROJECT (0501) AND TO THE SAN PABLO AVENUE BRIDGE PROJECT (0202) CEQA: The Bush Avenue Pocket Park Project is categorically exempt per CEQA Guidelines 15303(d) and (e), and Section 15304(b) and (f), as it only includes, respectively, new construction of small structures (e.g., play equipment, new water meter, new fence, etc.) and minor alterations of land (e.g., new landscaping, minor trenching and backfill where new surface is restored). The CEQA Notice of Exemption was filed at the Contra Costa County Clerk's Office on December 18, 2021.
Attachments: 1. Att A - RES Accepting Project and NOC 2025-01-21
PREPARED BY: MATTHEW BROWN DATE OF MEETING: 01/21/2025
SUBJECT:
TITLE
CONSIDER ADOPTING RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO (1) ACCEPTING WORK PERFORMED BY MICHAEL PAUL COMPANY INC FOR THE HAPPY FRIDAY PARK (ORIGINALLY BID AS BUSH AVENUE POCKET PARK) PROJECT (0502) AS COMPLETE; (2) DIRECTING A NOTICE OF COMPLETION TO BE PREPARED AND FILED WITH THE COUNTY RECORDER; AND (3) RE-ALLOCATING UNUSED APPROPRIATED FUNDS FROM THE HAPPY FRIDAY PARK (0502) IN THE AMOUNT OF $105,234.14 TO THE MCNEIL PARK PROJECT (0501) AND TO THE SAN PABLO AVENUE BRIDGE PROJECT (0202)

CEQA: The Bush Avenue Pocket Park Project is categorically exempt per CEQA Guidelines 15303(d) and (e), and Section 15304(b) and (f), as it only includes, respectively, new construction of small structures (e.g., play equipment, new water meter, new fence, etc.) and minor alterations of land (e.g., new landscaping, minor trenching and backfill where new surface is restored). The CEQA Notice of Exemption was filed at the Contra Costa County Clerk's Office on December 18, 2021.

Label
CITY MANAGER RECOMMENDATION
Recommendation
Adopt Resolution

BODY
COUNCIL PRIORITY WORKPLAN STATEMENT
Major Policy Goal: Build a Healthy Community - 109 Develop Public Facilities for Active Living is a priority item under the FY 2023-25 Council Priority Workplan, effective on May 1, 2023.

BACKGROUND
The Happy Friday Park Project (0502) (originally bid as Bush Avenue Pocket Park Project) was a proposed multi-benefit, community-informed pocket park project that transformed the 1701 Bush Avenue vacant lot into a pocket park with swings, exercise loop, fitness machines, shade structures, other play equipment, and native plants-all elements residents stated they would like to see.

On December 23, 2021, California State Parks approved the City of San Pablo's Per Capita allocation of Proposition 68 funds in the amount of $196,899. On March 1, 2022, the City was notified that the City of San Pablo's Clea...

Click here for full text