File #: 25-015    Version: 1 Name:
Type: RESOLUTION Status: Passed
File created: 12/17/2024 In control: City Council
On agenda: 1/21/2025 Final action: 1/21/2025
Title: CONSIDER ADOPTING A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO (1) ACCEPTING WORK PERFORMED BY CENTRAL ROOFING, INC. FOR THE COMMUNITY CENTER ROOF REPLACEMENT PROJECT (0107) AS COMPLETE, AND (2) DIRECTING CITY ENGINEER TO FILE A NOTICE OF COMPLETION WITH THE COUNTY RECORDER CEQA: This proposed action is not a project as defined by CEQA.
Attachments: 1. Att A - Resolution Comm Ctr Roof Accept Project as Complete 2025-01-21

PREPARED BY:  ALLAN A. PANGANIBAN                                          DATE OF MEETING: 01/21/2025 

SUBJECT:                     

TITLE

CONSIDER ADOPTING A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO (1) ACCEPTING WORK PERFORMED BY CENTRAL ROOFING, INC. FOR THE COMMUNITY CENTER ROOF REPLACEMENT PROJECT (0107) AS COMPLETE, AND (2) DIRECTING CITY ENGINEER TO FILE A NOTICE OF COMPLETION WITH THE COUNTY RECORDER

 

CEQA: This proposed action is not a project as defined by CEQA.

 

 

Label

CITY MANAGER RECOMMENDATION

Recommendation

Adopt Resolution

 

Body

Compliance statements

FY 2023-2025 Council Priority Workplan Compliance Statements:

Build a Healthy Community is a Major Policy Goal contained in the Fiscal Year 2023-25 City Council Priority Workplan, effective March 1, 2023. 

 

CEQA Compliance Statement

This Project was previously determined to be categorically exempt from environmental review pursuant to CEQA Guidelines Section 15301, Existing Facilities, as it consists of operation, repair, maintenance, permitting, leasing, licensing, or minor alteration of existing public or private structures, facilities, mechanical equipment, or topographical features, involving negligible or no expansion of use beyond that existing at the time of the lead agency’s determination.  The CEQA Notice of Exemption was filed with the County Recorder on July 26, 2024. 

 

BACKGROUND

The project goal was to replace the Community Center Roof which consisted of clay tile materials.  It started experiencing leaks in 2019.  The new roof consists of standing seam metal roof. 

 

The roof materials were purchased from a vendor who participates in the California Multiple Award Schedules (CMAS) program provided by California’s Department of General Services.  On June 10, 2024, City Council authorized the purchase of roofing materials for the roof replacement project pursuant to Resolution 2024-082. 

 

City Council awarded the construction contract on July 1, 2024 pursuant to Resolution 2024-091 to Central Roofing, Inc. in the amount of $254,000 with a 15% contingency for a total authorization not to exceed $292,100.  The Notice to Proceed became effective on August 19, 2024.  Work was substantially completed during the week of September 9, 2024.  Several punch list items were concluded by October. 

 

A contract change order was issued on December 17, 2024, which included installing temporary roofing materials for a rare August rain shower, installing roof valley system that include transitions between old and new metal roof, and adding a vented ridge closure and skylights. 

 

The final contract amount to Central Roofing Inc. is $291,696.99.  The proposed final estimate letter was issued to Central Roofing Inc. on December 19, 2024.  The final project costs are indicated on the table below.  Central Roofing Inc. has concurred and accepted the final estimate through a correspondence dated December 19, 2024. 

 

The City Engineer has determined that the above work has been completed in accordance to the plans and specifications. 

 

By adopting the attached resolution, the Council will accept the work as complete and authorize the City Engineer to issue a Notice of Completion.  This action will allow the title of the work to transfer from the Contractor to the City and will enable processing the final payment. 

 

The City is holding 5% retention on this project.  After the prescribed period of recordation of the Notice of Completion, the City will release the final retention. 

 

In order to maintain this new infrastructure, maintenance will need to be performed on a regular basis.  Tasks such as cleaning gutters and downspouts and annual inspections will be ongoing with an approximate costs of $2,000 per year. 

 

FISCAL IMPACT

 

Project Budget

The project budget was derived from the Building and Facilities Maintenance Reserve Fund (Fund 130). City Council appropriated a total amount of $544,600 to the project through Resolutions 2024-082 and 2024-091. 

 

The appropriated project budget and project expenditures are as follows:

 

 

Account

Task Code

Amount

Resolution

Materials

130-0000-49999

320-0107-43604-IBF-425

$203,500

2024-082

Construction

130-0000-49999

320-0107-43604-IBF-425

$292,100

2024-091

Construction Management

130-0000-49999

320-0107-43605-IBF-425

$37,000

2024-091

Project Management & Building Permit

130-0000-49999

320-0107-43600-IBF-425

$12,000

2024-091

Total

 

 

$544,600

 

 

Project Expenditures

 

Description

Vendor

Amount

Materials

The Garland Company

$170,164

Construction

Central Roofing Inc.

$291,697

Construction Management

Park Engineering

$  20,800 (Estimated)

Project Management

Mercurio Engineering

$   7,670

Building Permit

Building Division

$      836

TOTAL

$491,167

 

The remaining estimated funds in the amount of $53,433 will be revert back to the Building and Facilities Maintenance Reserve Fund balance (Fund 130). If actual expenditures are less then estimated costs, the difference of unused funds will also revert to the Building and Facilities Maintenance Reserve Fund balance.  

 

ATTACHMENTS:

Att A - Resolution