Title: CONSIDER ADOPTING RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO AUTHORIZING THE CITY MANAGER TO (1) RE-ALLOCATE REMAINING GENERAL FUNDS IN THE AMOUNT OF $157,094 FROM THE RUMRILL BOULEVARD COMPLETE STREETS PROJECT (0700) TO THE SAN PABLO DAM ROAD GATEWAY I-80 IMPROVEMENTS PROJECT (0605); (2) TRANSFER CALTRANS ALTERNATIVE COMPLIANCE FUNDS IN THE AMOUNT OF $500,000 AND TESORO REFINERY ALTERNATIVE COMPLIANCE FUNDS IN THE AMOUNT OF $32,945 TO ACCOUNT CODE 910-3310-20703 FOR POST-CONSTRUCTION MAINTENANCE; AND (3) REVERT REMAINING SB 1 ROAD MAINTENANCE AND REHABILITATION ACCOUNT (RMRA) FUNDS IN THE AMOUNT OF $135,851 TO THE RMRA FUND BALANCE AND REMAINING MEASURE J LOCAL STREET MAINTENANCE (LSM) FUNDS IN THE AMOUNT OF $256,683 TO THE MEASURE J LSM FUND BALANCE CEQA: The Rumrill Boulevard Complete Streets Project (Project) is categorically exempt under the California Environmental Quality Act (CEQA), Section 15301, Existing Facilities (Class 1) of the CEQA Regulations, on the basi...
Attachments: 1. RES 2025-065 Rumrill Reallocate and Remit Remaining Funds

PREPARED BY:  MATTHEW BROWN                                           DATE OF MEETING:   05/19/2025

SUBJECT:                     

TITLE

CONSIDER ADOPTING RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO AUTHORIZING THE CITY MANAGER TO (1) RE-ALLOCATE REMAINING GENERAL FUNDS IN THE AMOUNT OF $157,094 FROM THE RUMRILL BOULEVARD COMPLETE STREETS PROJECT (0700) TO THE SAN PABLO DAM ROAD  GATEWAY I-80 IMPROVEMENTS PROJECT (0605); (2) TRANSFER CALTRANS ALTERNATIVE COMPLIANCE FUNDS IN THE AMOUNT OF $500,000 AND TESORO REFINERY ALTERNATIVE COMPLIANCE FUNDS IN THE AMOUNT OF $32,945 TO ACCOUNT CODE 910-3310-20703 FOR POST-CONSTRUCTION MAINTENANCE; AND (3) REVERT REMAINING SB 1 ROAD MAINTENANCE AND REHABILITATION ACCOUNT (RMRA) FUNDS IN THE AMOUNT OF $135,851 TO THE RMRA FUND BALANCE AND REMAINING MEASURE J LOCAL STREET MAINTENANCE (LSM) FUNDS IN THE AMOUNT OF $256,683 TO THE MEASURE J LSM FUND BALANCE

 

CEQA: The Rumrill Boulevard Complete Streets Project (Project) is categorically exempt under the California Environmental Quality Act (CEQA), Section 15301, Existing Facilities (Class 1) of the CEQA Regulations, on the basis that the Project involves repair and minor alteration to the existing public streets, sidewalks, gutters, and similar facilities.  The Notice of Exemption was filed and recorded with the Contra Costa County Clerk on January 7, 2018.  Moreover, since the Project is also receiving federal funding, the Project was also determined to be categorically exempt under the National Environmental Policy Act (NEPA), Section 23 CFR 771.117 (c)(3). The Notice of Exemption for NEPA was filed on March 14, 2018 and revalidated on August 7, 2020 by the California Department of Transportation (Caltrans). 

 

Label

CITY MANAGER RECOMMENDATION

Recommendation

Adopt Resolution

 

Body

Compliance statements

FY 2025-2027 Council Priority Workplan Compliance Statements:

Major Policy Goal: Build a Healthy Community - 109 Develop Public Facilities for Active Living (Parks, Open Space, Sidewalks, Trails, Bike Lanes, Etc.)  is an adopted policy item contained in the FY 2025-27 Adopted City Council Priority Workplan, effective April 7, 2025.

 

BACKGROUND

The Rumrill Boulevard Complete Streets Project was a 1.7-mile-long comprehensive roadway improvement project that modified Rumrill Boulevard between Costa Avenue and San Pablo Avenue (Project).  The Project improved safety in and along the Rumrill Boulevard for all users including motorists, bicyclists and pedestrians.

 

The final reconciled Project expenditures are $24,284,572 and was funded with the following funding sources, which included $18,504,583 in grant and Alternative Compliance funds, $1,214,610 in local road funds, and $4,565,379 in local General Funds/ARPA. 

 

Project Funding

Agency

Funding Source

Amount

Metropolitan Transportation Commission (MTC)

Transportation Development Act (TDA) Article 3

$     85,000

City of San Pablo

Road Maintenance Rehabilitation Act (RMRA)

$   296,325

Tesoro Refinery

Alternative Compliance

$   395,409

Environmental Protection Agency (EPA)

SF Bay Water Quality Improvement Fund

$   864,634

Contra Costa Transportation Authority (CCTA)

Measure J Pedestrian, Bike, and Trail Facilities (PBTF)

$ 1,000,000

State Coastal Conservancy (SCC)

Proposition 1; Proposition 68

$ 1,150,000

City of San Pablo

Measure J Local Street Maintenance (LSM)

$ 1,310,819

California Department of Transportation (Caltrans)

Local Partnership Program (SB1 LPP)

$ 3,200,000

California Department of Transportation (Caltrans)

Alternative Compliance

$ 3,500,000

California Natural Resources Agency (CNRA)

Urban Greening Grant Program: Greenhouse Gas Reduction Fund

$ 3,999,540

California Department of Transportation (Caltrans)

Active Transportation Program

$ 4,310,000

City of San Pablo

Local Funds and American Rescue Plan Act (ARPA)

$ 4,722,473

 

Total

$24,834,200

 

Project Expenditures

Project Phases

Expenditures

Construction

$18,787,746

Construction Management

$  2,325,952

Design/Environmental/Right of Way (ROW)

$  2,451,439

Miscellaneous

$     186,490

Post-Construction Maintenance

$     532,945

Total

$24,284,572

 

At Project completion there was $549,628 remaining in the project budget. Staff is recommending to re-allocate and revert remaining funds as outlined in the Fiscal Impact Section.

 

As part of the Alternative Compliance funding agreements with Caltrans and Tesoro, City staff negotiated $532,945 in upfront payment to support 10 years of post-construction maintenance related to bioretention/landscaping and various storm drain infrastructure.  To comply with these funding agreements, staff recommends transferring these funds to a Fund 910, interest-bearing account as outlined below.

Agency

Funding Source

Amount Appropriated

Post-Construction Maint. Amount Per Funding Agreement

Caltrans

Alternative Compliance

$3,500,000

$  500,000

Tesoro Refinery

Alternative Compliance

$   395,409

$    32,945

 Total

$3,895,489

$  532,945

 

Funds with remaining balances include Local General Funds, RMRA, and LSM as shown in the table below. Staff is requesting to re-allocate local General Funds to the San Pablo Dam Road Gateway I-80 Improvements Project (0605), and to revert remaining RMRA funds and Measure LSM funds to respective fund balances as outlined below.

 

Funding Source

Amount Appropriated

Expended

Amount Remaining

RMRA

$   296,325

$   160,474

$135,851

Measure J LSM

$1,310,819

$1,054,136

$256,683

Local Funds

$4,722,473

$4,565,379

$157,094

 Total

$6,329,617

$5,779,989

$549,628

 

FISCAL IMPACT

The fiscal impacts are outlined in the tables below. 

 

Action

Funding Source

FROM: Account

TO: Account

Amount

Re-allocate

General Funds

320-0700-43604

320-0605-43604

$157,094

Transfer

Alternative Compliance (Caltrans)

320-0700-43604

910-3310-20703

$500,000

Transfer

Alternative Compliance (Tesoro Refinery)

320-0700-43604

910-3310-20703

$32,945

Totall

$690,039

 

Funding Source

Amount Appropriated

Expended

Amount to Revert

RMRA

$    296,325

$    160,474

$135,851

Measure J LSM

$ 1,310,819

$ 1,054,136

$256,683

 Total  

$ 1,607,144

$ 1,214,610

$392,534

 

Ongoing Maintenance Division staffing resources will be required for the new facilities in order to function properly and preserve the neat appearance of the corridor The additional maintenance resources are estimated to be 2.5 FTE of staff time in the Maintenance Division.

 