Legislation Details

File #: 24-069    Version: 1 Name:
Type: RESOLUTION Status: Passed
File created: 2/7/2024 In control: City Council
On agenda: 2/20/2024 Final action:
Title: CONSIDER ADOPTING RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO (1) APPROVING THE PLANS AND SPECIFICATIONS FOR THE BUSH AVENUE POCKET PARK PROJECT (0502) (PROJECT), (2) AWARDING MICHAEL PAUL COMPANY, INC., A CONSTRUCTION CONTRACT FOR THE PROJECT, (3) AUTHORIZING THE CITY MANAGER TO EXECUTE AN AGREEMENT WITH MICHAEL PAUL COMPANY, INC. IN AN AMOUNT OF $571,887.66 WITH A 15% CONTINGENCY FOR TOTAL AUTHORIZATION NOT TO EXCEED $657,671 AND (4) REAPPROPRIATING FUND 120 FUNDS IN THE AMOUNT OF $247,002 FROM THE FULL TRASH CAPTURE DEVICE PROJECT (0304) TO THE BUSH AVENUE POCKET PARK PROJECT (0502) CEQA: The Bush Avenue Pocket Park Project is categorically exempt per CEQA Guidelines Sections 15303(d) and (e), and Sections 15304(b) and (f), as it only includes, respectively, new construction of small structures (e.g., play equipment, new water meter, new fence, etc.) and minor alterations of land (e.g., new landscaping, minor trenching and backfill where new surface is restored). The C...
Attachments: 1. Att A - RES Adopting Plans and Specifications Bush Ave 2024-02-20, 2. Att B - Contract

PREPARED BY:  MATTHEW BROWN                                           DATE OF MEETING:   02/20/2024

SUBJECT:                     

TITLE

CONSIDER ADOPTING RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO (1) APPROVING THE PLANS AND SPECIFICATIONS FOR THE BUSH AVENUE POCKET PARK PROJECT (0502) (PROJECT), (2) AWARDING MICHAEL PAUL COMPANY, INC., A CONSTRUCTION CONTRACT FOR THE PROJECT, (3) AUTHORIZING THE CITY MANAGER TO EXECUTE AN AGREEMENT WITH MICHAEL PAUL COMPANY, INC. IN AN AMOUNT OF $571,887.66 WITH A 15% CONTINGENCY FOR TOTAL AUTHORIZATION NOT TO EXCEED $657,671 AND (4) REAPPROPRIATING FUND 120 FUNDS IN THE AMOUNT OF $247,002 FROM THE FULL TRASH CAPTURE DEVICE PROJECT (0304) TO THE BUSH  AVENUE POCKET PARK PROJECT (0502)

 

CEQA: The Bush Avenue Pocket Park Project is categorically exempt per CEQA Guidelines Sections 15303(d) and (e), and Sections 15304(b) and (f), as it only includes, respectively, new construction of small structures (e.g., play equipment, new water meter, new fence, etc.) and minor alterations of land (e.g., new landscaping, minor trenching and backfill where new surface is restored). The CEQA Notice of Exemption was filed at the Contra Costa County Clerk's Office on December 18, 2021.

 

Label

CITY MANAGER RECOMMENDATION

Recommendation

Adopt Resolution

 

Body

COUNCIL PRIORITY WORKPLAN statement

Major Policy Goal: Build a Healthy Community - 109 Develop Public Facilities for Active Living is a Major Policy Goal under the FY 2023-25 Council Priority Workplan, effective on May 1, 2023. 

 

BACKGROUND

The Bush Avenue Pocket Park Project is a proposed multi-benefit, community-informed pocket park project that will transform the 1701 Bush Avenue vacant lot into a pocket park with swings, exercise loop, fitness machines, shade structures, other play equipment, and native plants-all elements residents stated they would like to see. 

 

On December 23, 2021, California State Parks approved the City of San Pablo’s Per Capita allocation of Proposition 68 funds in the amount of $196,899.  On March 1, 2022, the City was notified that the City of San Pablo’s Clean California Grant Program (CCLGP) grant application was successful and the City had been awarded $377,000.  On March 21, 2022, through Resolution 2022-045, the Council accepted and appropriated the funds from the CCLGP grant and the Proposition 68 Per Capita allocation to the Bush Avenue Pocket Park Project (0502). 

 

On August 1, 2022, City Council through Resolution 2022-315 awarded the design contract for the Project to Gates + Associates.  On December 20, 2023, staff advertised the notice inviting bids for construction for the Project and received six (6) bids:

 

1)

Michael Paul Company INC

Petaluma, CA

$571,887.66

2)

Redwick Construction Company

Oakland, CA

$584,017.00

3)

ERA Construction

San Pablo, CA

$638,084.68

4)

JPB Design Inc

Orangevale, CA

$644,342.00

5)

Mark Lee and Yong Kay DBA Bay Construction Company

Oakland, CA

$706,356.25

6)

Kerex Engineering

Pleasant Hill, CA

$739,911.00

 

The lowest responsive and responsible bidder was Michael Paul Company, Inc., from Petaluma, CA, with a bid amount of $571,887.66.  Staff reviewed the bid and determined it to be responsive.  Staff checked the contractor’s references from the North Bay area counties agencies and received positive feedback. 

 

 Staff recommends that City Council:

 

1.                     Approve the Plans and Specifications for the Bush Avenue Pocket Park Project (0502);

2.                     Award Michael Paul Company, Inc. the construction contract for the Project;

3.                     Authorize the City Manager to execute an agreement with Michael Paul Company, Inc. in an amount not to exceed $571,887.66, with a 15% construction contingency authorization, for a total contract authorization not to exceed $657,671; and

4.                     Re-appropriate available Fund 120 Funds in the amount of $247,002 from the Full Trash Capture Device Project (0304) to the Bush Avenue Pocket Park Project (0502) to augment the existing funds and be able to complete the construction of the Project.

 

Construction is scheduled to begin in March 2024 and is expected to be completed within 60 working days. 

 

FISCAL IMPACT

The fiscal impacts for the project are outlined in the tables below.

 

Action

FROM: Fund / Account Code

Amount

TO: Fund / Account Code

Amount

Re-appropriate

320-0304-43604-ARA-123

$247,002

320-0502-43604-ARA-123

$247,002

TOTAL APPROPRIATED

$247,002

 

Project Budget

Fund Source

Account Code

Amount

CA State Parks Proposition 68 Per Capita Grant

320-0502-43602-PCP-222 &  320-0502-43604-PCP-222

$196,899

Caltrans CCLGP Grant

320-0502-43600-CCA-222 &  320-0502-43604-CCA-222

$377,000

Street Lighting and Landscape Assessment District

320-0502-43604-SLD-322

$32,500

EBMUD Rental Revenues

320-0502-43602-OTH-522

$29,194

NPDES FY22 & FY23 Operating Budgets

320-0502-43600-GEN-422 &  320-0502-43600-GEN-423

$23,000

Fund 120

320-0502-43604-ARA-123

$247,002

FY22 CIP General Funds (Re-appropriated from the Citywide Slurry Seal Project)

320-0502-43602-GEN-422

$25,870

TOTAL PROJECT BUDGET

$931,465

 

Estimated Project Expenditures

Description

Amount

Design Consultant - Concept Design  (Groundworks Office)

$5,000

Project Management  (Harrison Engineering)

$23,672

Media Campaign

$71,050

Design Consultant  (Gates + Associates) - Includes 10% Contingency

$99,000

Construction Contract  (Michael Paul Company, Inc.) - Includes 15% Contingency

$657,671

Construction Management & Inspection  (GHD Engineering)

$70,072

Utilities  (Water Meter)

$5,000

 TOTAL ESTIMATED EXPENDITURES

 $931,465

 

 